GE Innova IGS 620 Preinstallation Manual page 183

Table of Contents

Advertisement

Table 5-5: System FEEDER from hospital
Feeder run length:
Feeder run length:
NOTE:
Chapter 5 Electrical Requirements
Power supply voltage 480 V
Panel (PDB) to C1 run in m
8 (26)
16 (52)
10 m (30
ft)
2/0
20 m (70 ft)
2/0
30 m (100 ft)
2/0
40 m (130 ft)
2/0
50 m (160 ft)
2/0
60 m (200 ft)
3/0
80 m (260 ft)
4/0
100 m (330 ft)
300
120 m (390 ft)
400
8 m
10 m
35
20 m
35
30 m
50
40 m
50
50 m
70
60 m
95
80 m
120
100 m
185
120 m
240
NOTICE
Recommended feeder cable section in mm² : for PHASES, NEUTRAL & GROUND PDB input termi‐
nals accept 35² to 95². Bigger cables needs a size reduction before PDB entry.
Increasing transformer power will decrease its voltage loss and feeder cables section. To be calculated site
by site.
Innova
IGS 620, Innova
TM
(ft)
24 (79)
2/0
2/0
2/0
2/0
2/0
3/0
2/0
250
3/0
300
4/0
400
350
600
see
500
Note
see
600
Note
Power supply voltage
380 V
Panel (PDB) to C1 cabinet run
16 m
24 m
8 m
35
35
35
35
70
35
70
95
35
70
120
50
95
185
70
120
240
70
185
300
95
see
240
note
150
see
300
note
185
IGS 630 Preinstallation Manual
TM
Direction 5694389-1-1EN, Revision 2
WARNING
RECOMMENDED FEEDER CABLE
GAUGE : FOR PHASES, NEUTRAL &
GROUND PDB INPUT TERMINALS
ACCEPT 2/0 AND 3/0 AWG. BIGGER
CABLES NEEDS A SIZE REDUCTION
BEFORE PDB ENTRY.
400 V
16 m
24 m
8 m
35
35
35
35
50
35
50
70
35
70
95
50
95
120
70
95
185
70
150
300
95
240
see note
120
300
see note
185
415 V
16 m
24 m
35
35
35
50
50
70
70
95
95
120
95
150
120
240
185
see note
240
see note
183