Step 4. Erection of the mast.
ATTENTION:
TO ASSEMBLE THE MASTS WILL USE, PREFERABLY A BUILDING SITE CRANE, OR
AN AUXILIARY DAVIT (OPTIONAL). NEVER MANIPULATE THE MASTS BY HAND.
IT´S RECOMMENDED TO MOUNT SECTIONS OF 6 M. (4 MODULES) ON THE
GROUND, AND FASTEN THE WHOLE GROUP TO THE MACHINE WITH THE HELP
OF A CRANE. THE FIRST MAST OF THE MACHINE, COUPLED TO THE BASE FRAME,
INCLUDES THE NUMBER ID OF THE MACHINE.
IMPORTANT:
TO MOUNT THE MACHINE, AND FOR INSPECTION AND MAINTENANCE TASKS,
ALWAYS USE THE "MANUAL" MODE OF OPERATION (CAGE CONTROL).
SEE CHAPTER 3 BEFORE STARTING HOIST ERECTION.
©
ALBA-MACREL GROUP, S.L.
MAST TÉCHNICAL DATA
Weight: 39 Kg
Rack unión:
Welded
Mast screws:
(3x) Screw M12x90 DIN 931 8.8
Whaser A13 DIN 125
Self-locking nut M13 DIN 985
Torque (max):
85 N·m
USER´S MANUAL
Pag. 17