5.1.1 Site Planning

Floor Loading Capacity
Ensure that the floor can bear the weight of the UPS and its optional components.
Installation Environment
Clearances
Ensure that the distance between UPS air vents and a wall or obstacle is greater
than or equal to 500 mm.
Clearances should be reserved around the chassis to facilitate ventilation and
operations. Clearances of at least 500 mm should be reserved in front of and
behind the chassis.
Figure 5-1 Clearances for the 6 kVA model (unit: mm)
Figure 5-2 Clearances for the 10 kVA model (unit: mm)
Issue 03 (2023-08-20)
Do not install the UPS in a hot, cold, or damp place that is beyond the
technical specifications.
Keep the UPS far away from water, heat sources, and flammable and
explosive substances. Install the UPS in an environment free of dust, volatile
gas, salt, and corrosive materials. Avoid direct sunlight.
Do not install the UPS in environments with conductive metal scraps in the
air.
NO TICE
Copyright © Huawei Digital Power Technologies Co., Ltd.
5 Installation and Cable Connection
52

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ups2000-h-6krtl-lUps2000-h-10krtl-l

Table of Contents