Site Preparation Pre-Installation Checklist + Sign off

Site Preparation Pre-Installation Checklist + Sign off
Introduction
This is the Arizona 1300 hardware requirements checklist.
Requirements
(Tick check box if compliant, if not when is the compliance achieved)
Requirement:
Shock and Vibration
• Keep isolated from shears, punch presses, and guillo-
tines
Cleanliness
• Area should be reasonably clear of dust and other air-
borne particles
Should not be installed in areas shared by routing,
sanding, trimming or cutting equipment
Flooring/ Floor covering
• Concrete floor is ideal: minimum requirement is a
stiff, well-supported floor
• Vinyl tile or floor sealed with paint or other floor coat-
ing materials
• Do not install on carpet.
Operating space
• Minimum space GT: 7,65 x 4,8 m / 25 x 15.7 Ft
• Minimum space XT: 8 x 6,6 m / 26.3 x 21.6 Ft
Ventilation and Room Volume
Sufficient room ventilation secured. Typically:
• > 1200 m³/hour (< 4 hours usage/day)
• > 2300 m³/hour (> 4 hours usage/day)
• Alternatively: include Duster 3000
Room Temperature
• Not lower than: 18ºC (64ºF)
• Not higher than: 30ºC (86ºF)
• Temperature Range: Maintained within a 4ºC (7ºF)
band
Humidity
• Relative humidity: 30% to 70% (Non-condensing)
Altitude
• 2750m (9020 feet) maximum
44
Chapter 7 - Site Preparation checklists
Check
When / Action
.
.
.
.
.
.
.
.