Delivery And Handling; Transport; Assembly - Nibe F110 Installation Manual

Hot water heat pump
Hide thumbs Also See for F110:
Table of Contents

Advertisement

Delivery and handling

Transport

F110 should be transported and stored vertically in a dry
place.
However, the F110 can be carefully laid on its back when
being moved into the building. The centre of gravity is in the
top section.

Assembly

Position F110 on a solid foundation indoors that withstands
water and the weight of the product.
Use the product's adjustable feet to attain a horizontal
and stable set-up.
20-55 mm
30 - 50 mm
Since water comes from F110, the area where F110 is loc-
ated must be equipped with floor drainage.
Because water comes from F110, the floor coating is im-
portant. A waterproof floor or floor membrane is recom-
mended.
Install with its back to an outside wall, ideally in a room
where noise does not matter, in order to eliminate noise
problems. If this is not possible, avoid placing it against a
wall behind a bedroom or other room where noise may be
a problem.
Wherever the unit is located, walls to sound sensitive
rooms should be fitted with sound insulation.
Route pipes so they are not fixed to an internal wall that
backs on to a bedroom or living room.
The installation area always has to have a temperature of
at least 10 °C and max. 30 °C.
NIBE F110
0
R
INSTALLATION AREA
Leave a free space of 800 mm in front of the product. Leave
free space between F110 and wall/other machinery/fit-
tings/cables/pipes etc. It is recommended that a space of
at least 10 mm is left to reduce the risk of noise and of any
vibrations being propagated.
NOTE
Ensure that there is sufficient space (300 mm)
above F110 for connecting ventilation ducts.
Chapter 2 | Delivery and handling
800
7