Commissioning and adjusting

Preparations

1.
Check that the display is off.
2.
Check that the filling valves are fully closed.
Caution
Check the temperature limiter (FQ10) in the heat
pump. It may have tripped during transport.

Filling and venting

FILLING THE HOT WATER HEATER
1.
Open a hot water tap in the house.
2.
Open the filling valve (QM30). Afterwards, this valve
must be fully open during operation.
3. When the water that comes out of the hot water tap is
no longer mixed with air, the water heater is full and the
tap can be closed.
VENTING
Vent the heat pump with the vent valve (QM25) until there
is no air in the water that comes out of the valve. Repeat
venting after operating for a while.
QM30
FQ10
NIBE F110
QM25

Start-up and inspection

START GUIDE
NOTE
There must be water in the water heater before
the heat pump is started. Check that the thermo-
stat (BT35) is on max.
1.
Start F110 by connecting the supply cable.
2.
Follow the instructions in the display's start guide. If the
start guide does not start when you start the F110, you
can start it manually in menu 5.7.
TIP
See page 23 for a more in-depth introduction to
the heat pump's control system (operation, menus
etc.).
Commissioning
The first time the installation is started a start guide is star-
ted. The start guide instructions state what needs to carried
out at the first start together with a run through of the in-
stallation's basic settings.
The start guide ensures that the start-up is carried out cor-
rectly and, for this reason, cannot be skipped.
Operation in the start guide
Arrows to scroll through window in start guide
1.
Press the up or down button until one of the arrows in
the top left corner (at the page number) has been
marked.
2.
Press the OK or Back button to move backwards or for-
wards in the start guide.
If the start guide is left on this page it
closes automatically in
See page 23 for a more in-depth introduction to the heat
60 min
pump's control system.
SETTING THE VENTILATION (EXHAUST AIR)
The ventilation must be set according to applicable stand-
ards. The fan speed is set in menu 5.1.5 - "fan speed".
The ventilation must be set according to applicable stand-
ards. The fan speed is set in menu 7.1.4.1 - "Fan speed, ex-
haust air".
Even if ventilation is roughly set at installation it is important
that a ventilation adjustment is ordered and permitted.
Chapter 6 | Commissioning and adjusting