Huawei SmartACU2000B Quick Manual page 11

Smart array controller
Hide thumbs Also See for SmartACU2000B:

Advertisement

3
Installing the Cabinet
3.1
Preparations
Installation Space
3.2
Installing the Mounting Bracket
The mounting bracket has four groups of tapped holes, each group containing four tapped holes.
Mark any hole in each group based on site requirements and mark four holes in total. Two round
holes are preferred.
Wall-mounted Installation
Avoid drilling holes in the water pipes and power cables buried in the wall.
To prevent dust inhalation or contact with
eyes, wear safety goggles and an anti-dust
mask when drilling holes.
Clean up any dust in and around the holes
using a vacuum cleaner and measure the
hole distances. If the holes are inaccurately
positioned, drill holes again.
Level the head of the expansion sleeve
with the concrete wall after removing the
bolt, spring washer, and flat washer.
Otherwise, the mounting bracket will not be
securely installed on the concrete wall.
Bolts
When the cabinet is installed on a wall, you
need to prepare M12 x 60 stainless steel
exploded expansion bolts.
• If the cabinet is installed on a support or a
pole, use the M12 x 40 bolt assemblies
delivered with the cabinet.
1. Mark hole positions.
10