Installation - SAMES KREMLIN PU3000 2L 53/1 Translation From The Original Manual

Electronic mixing machine
Table of Contents

Advertisement

The control box must be connected to a supply fitted with a ground.
The bracket of the pumps is fitted with a ground cable. That must be grounded.
Do not install the paint drums underneath the pumps or the electric equipment.
Place them in front of the frame. Install a cover on the drums to reduce the
diffusion of gas and vapours in the booth.
The electrical cable connecting the chassis mounted electric components to the
control box must be installed so that at no time is any risk from mechanical
P
damage, chemical corrosion or excessive heat. Please ensure that the wiring loom
is kept separate from any other electrical cables that are not intrinsically safe.

INSTALLATION

There are different ways to install the PU 3000 to answer to the majority of the installations.
The control box of the PU 3000 mixing machine must be installed outside the spray
booth in a safe area.
Assembly for piloting outside the booth :
The machine is in two parts to enable the
control box to be fitted outside the booth
(cable of 8 m / 26.2 ft between the 2
elements).
Nota : Drawing of a unit, model PU 3000
Airmix
Assembly for machine control in the
booth :
There is a booth mounting control kit
(available in option).
That kit enables the user to fix the control
box on the booth by means of a glass panel
and to control the machine inside the
spraybooth.
The control is carried out thanks to a
magnet provided with the machine. The
distance between the control box and the
fluid frame is of 8 m / 26.2 ft (cable supplied
with the machine).
SAMES KREMLIN
Page 15
Manual : 573.199.112

Advertisement

Table of Contents
loading

Table of Contents