Unigas G335A Installation Manual page 23

Table of Contents

Advertisement

Integrated proving system (burners equipped with LME7x, LMV, LDU)
This paragraph describes the integrated proving system operation sequence:
At the beginning both the valves (EV1 and EV2) must be closed.
Test space evacuating: EV2 valve (burner side) opens and keep this position for a preset
time (td4), in order the bring the test space to ambient pressure.Test atmospheric pressure:
EV2 closes and keep this position for a preset time (test time td1). The pressure switch
PGCP has not to detect a rise of pressure.
Test space filling: EV1 opens and keep this position for a preset time (td3), in order to fill the
test space.
Test gas pressure: EV1 closes and keep this position for a preset time (td2). The pressure
switch PGCP has not to detect a pressure drop down.
If all of the test phases are passed the proving system test is successful, if not a burner lockout
happens.
On LMV5x and LMV2x/3x and LME73 (except LME73.831BC), the valve proving can be
parameterized to take place on startup, shutdown, or both.
On LME73.831BC the valve proving is parameterized to take place on startup only.
OIL TRAIN CONNECTIONS
Hydraulic diagrams for light oil supplying circuits
1
3
GRAVITY CIRCUIT
SUCTION CIRCUIT
2
Key
1 Manual valve
2 Light oil filter
3 Light oil feeding pump
4 One way valve
5 Flexible hoses
6 Relief valve
NOTE: in plants where gravity or ring feed systems are provided,
install an automatic interception device.
23
PART II: INSTALLATION
PS
EV2
EV1
EV1
EV2
PGCP
/
RING CIRCUIT

Advertisement

Table of Contents
loading

This manual is also suitable for:

G258aG380aG400a

Table of Contents