5 Mounting and start-up

NOTICE
!
Risk of malfunction due to incorrect sequence
of mounting, installation and start-up.
Observe the prescribed sequence.
Î Sequence:
1. Remove the protective caps from the
pneumatic connections.
2. Mount the solenoid valve.
Î Section 5.1 onwards
3. Perform pneumatic installation.
Î Section 5.3 onwards
4. Perform electrical installation.
Î Section 5.4 onwards
EB 3966 EN

5.1 Installation

Any mounting position may be used. The fol-
lowing applies concerning the installation:
Î Install the solenoid valve in such a way
that the cable entry faces downward (in
cases where this is not possible, mount it
in the horizontal position).
Î On mounting, make sure that 200 mm or
more clearance is kept above the enclo-
sure cover.
Mounting and start-up
25