UDS-3 installation must be performed after reading carefully instructions indicated in this manual.
After mechanical installation, follow these instructions:
Choose the right batteries, check autonomy that plant must grant in case of 230Vac mains loss
Connect UDS-3 panel to 230Vac mains with a tri-polar cable: phase, neutral and ground (ground
conductor must be longer than the other two) and must be fixed with a small band to the case so
that it can't be pulled off accidentally
Mains connection must be done respecting the following:
Open general 230Vac power switch of the plant
Remove CNA terminal board from the control panel
Connect power cable to CNA terminal board
Connect CNA terminal board to the control panel
Close mains 230Vac switch
Install and connect batteries as shown in this manual (see p.34)
When the control panel is powered check the following conditions:
Voltage-presence green led ON
General fault yellow led blinking
Continuous buzzer sound
Press the "SOUNDER SILENCE" key, buzzer will silence.
Press F4 to show faults, remove possible causes.
Press "Escape" and then RESET, the display will show a level 2 password request.
Type the password and press enter to confirm and check the following conditions:
Voltage-presence green led ON
General fault yellow led blinking
No fault signalling on display
To configure UDS-3 control panel, see programming chapter in this manual
PAGE - 35
NOTIFIER ITALIA
S
T
A
R
T
-
U
P
S
T
A
R
T
-
U
P
Installation and operating manual
Doc. M-205.1-UDS3N-ENG Rev A.1
UDS-3
UDS-3_manu

Advertisement

Table of Contents
loading

Table of Contents