Installation
3.8 On-Site Insulation Test
For customers who want to do on-site insulation test, please make sure:
1. The DC switches are in "OFF" position.
2. Apply one probe to the positions shown in Figure 3-27, the other to the ground.
It might cause damages to the inverter if probes are applied to inappropriate
positions.
OFF
DC Switch
SWITCH 1
SWITCH 2
SWITCH 1
SWITCH 2
ON
ON
OFF
OFF
Hi-pot / Insulation
Figure 3-27: Precautions for on-site insulation test
47