1. Installation requirements

To enable a smooth and simple installation of the Sego please ensure the customer has the following
prepared:
• Ensure the electrical supply is situated within 1 meter of the machines proposed location.
• Ensure the power supply is correct for the ordered machine:
• Sego
» Standard
: 1x 230V, 2190W, 13amp (or higher)
» North America
: 1x 120V, 1440W, 12amp (or higher)
• Ensure that the machine fits the proposed location.
• The water supply must be cold potable (drinking) water terminating in a shut off valve with a male 3/4"
connection. This must be within 1 meter of the machines proposed location.
• The water pressure must be between 1 - 10 bar.
NOTE: Water pressure must be measured as standing pressure AFTER any fitted water filtration.
• The machine must be immediately available to the engineer within a reasonable distance of the proposed install
site.
What the engineer can do:
• Upon arrival the fully trained engineer will complete the following;
• Unpack the machine and inspect for transit damage.
• Install the machine in the proposed location.
• Connect the power and water supply to the machine.
• Connect a water filtration system if ordered.
• Commission the machine and complete a function test ensuring full operation.
• Set the machine up to a standard recipe if no pre set recipe has been specified in advance.
• Make adjustments to beverages taste and size (based on the person on site presented as the management
representative).
• Setup the recommended dosage of the soluble ingredient of each drink.
• Check if the water volume dosage is correct, if not, a calibration must be performed.
• Train staff on machine maintenance, cleaning and operation.
• Leave the area tidy .
► Always follow the local and national safety regulations and standards for electrical devices during installation.
► Read the safety book carefully. The safety book is provded with the machine or can be downloaded from the Bravilor
Bonamat site
Ingredients you may need:
• Ingredients should be selected based on taste profiles and site requirements.
We do however provide the following direction:
» Roasted whole coffee beans.
» Cacao and/or topping (or other soluble ingredient)*
* Only use instant ingredients that are suitable for vending machines (contains a flowing agent).
* Use the recommended dosage as indicated on the packaging.
► Always follow the local and national safety regulations and standards for electrical devices during installation.
► The contents of the safety booklet supplied with the machine must be known to both the installer and the customer.
► The operator instructions can be downloaded from the Bravilor Bonamat site.