Huawei LUNA2000-200KWH-2H1 Quick Manual page 21

Smart string energy storage system
Hide thumbs Also See for LUNA2000-200KWH-2H1:
Table of Contents

Advertisement

2. Install mounting ears and lifting handles, and then secure the Smart PCS. The mounting
ears are delivered with the Smart PCS, and the lifting handles are delivered with the ESS.
At least four persons are required to install the Smart PCS.
When using the lifting handles, hold the handle end closer to the device.
4.6
(Optional) Installing the Maintenance Socket
The 220 V socket is prepared by the customer. The actual socket appearance may vary. This
guide describes only the installation method.
1. Remove the baffle plate in front
of the power distribution area.
2. Install the maintenance socket.
20