3.5 Verifying the Installation

Table 3-1
Table 3-1 Post-installation checklist
No.
1
2
3
2022-08-15
lists the check items.
Item
Cable routing
Cable connection
Cable connection to USB,
network, and other ports
Expected Result
Cables are routed properly and meet
engineering requirements.
All cables are connected securely and
correctly, and they are free of damage.
Bolts are tightened to specified torque
using a torque wrench.
Signal cables to USB, network, and
other ports are connected securely and
correctly.