6-4 Upgrading from SL-1 N (QCA58 cabinet) to Option 61
Upgrading from SL-1 N (QCA58 CE cabinet) to Meridian 1
Option 61
Shelf upgrades to Meridian 1 553-3001-253
1
Obtain printouts of all the characteristics (TN, loop, telephones and all
other assignments and features) of the existing system. Retain these
printouts for an after conversion check.
2
Using overlay program 43, perform a data dump.
3
Remove the covers from the CE cabinet.
4
Invoke emergency line transfer by setting the line transfer switch on
all QPC84 Power Monitor circuit packs to ON or 1.
•
Set the -48 V cabinet input breaker located on the power control
shelf or power distribution box in the CE cabinet to OFF.
•
Tag and disconnect the cables from all the faceplate connectors of
circuit packs located on the QSP41 CPU/MEM shelf.
•
Remove all circuit packs from the CPU/MEM shelf.
•
Tag and disconnect cables A, B, C and D from the end of the
CPU/MEM shelf.
•
Tag and disconnect the four power and ground leads connected to
the lugs on the end of the shelf backplane.
5
Remove mounting screws securing CPU/MEM shelf to cabinet frame
and remove shelf from cabinet.
•
Position new QSD60 CPU/MEM shelf in the position vacated by
the QSP41 CPU/MEM shelf and secure to cabinet frame with four
mounting screws.
6
Connect:
•
the four power and ground leads from cabinet power wiring
harness to the -48V 0, -48V 1, -48V GND and L GND lugs on the
end of the new CPU/MEM shelf backplane (Figure 6-1).
•
cables A, B, C and D to the connectors on the end of the shelf
(Figure 6-2).