5-4 Upgrading from SL-1 N (QCA23 cabinet) to Option 61
Upgrading from SL-1 N (QCA23 CE cabinet) to Meridian 1
Option 61
Shelf upgrades to Meridian 1 553-3001-253
1
Obtain printouts of all the characteristics (TN, loop, telephones and all
other assignments and features) of the existing system. Retain these
printouts for an after conversion check.
2
Using overlay program 43, perform a data dump.
3
Remove the covers from the CE cabinet.
Note: The system service will be interrupted and emergency service
(if provided) will be connected.
4
Invoke emergency line transfer by setting the line transfer switch on
all QPC84 Power Monitor circuit packs to ON or 1.
•
Set the -48 V cabinet input breaker located on the power control
shelf or power distribution box in the CE cabinet to OFF.
•
Tag and disconnect the cables from all the faceplate connectors of
circuit packs located on the QSD37 CPU/MEM shelf.
•
Remove all circuit packs from the CPU/MEM shelf.
•
Tag and disconnect cables A, B, C and D from the end of the
CPU/MEM shelf.
•
Tag and disconnect the four power and ground leads connected to
the lugs on the end of the shelf backplane.
5
Remove mounting screws securing CPU/MEM shelf to cabinet frame
and remove shelf from cabinet.
•
Position new QSD59 CPU/MEM shelf in the position vacated by
the QSD37 CPU/MEM shelf and secure to cabinet frame with
four mounting screws.
6
Connect: