8-8 Upgrading from SL-1 XN (QCA55 cabinet) to Option 71
Shelf upgrades to Meridian 1 553-3001-253
Set ENB/DIS faceplate switches on the CMA and CPU FN circuit
packs to ENB and invoke a SYSLOAD by pressing the RESET or
RS button on the CMA circuit pack on the QSD61 shelf.
16 Refer to 553-3001-400 for an interpretation of codes displayed on the
faceplate of the MSI circuit pack. Some of the normal codes which
may appear during SYSLOAD are;
A1 – when records are being read from disk.
00 – when the MSI power-up is completed.
10 – when the MSI is in an idle state.
17 Refer to 553-3001-400 for an interpretation of SYS and INI messages
printed on the TTY (if connected) and of codes appearing on the
maintenance display.
18 Wait for SYSLOAD to complete. After Sysload (SYS) and
Initialization (INI) are completed, invoke manual INI to abort
midnight routine. Load overlay program 22 and print issue package
and configuration. Verify customer data.
Note: The following steps will cause the system service to be
interrupted and emergency service (if provided) will be connected.
19 Set the ENB/DIS switches on the SCG (or CC) and SBE circuit packs
on the QSD61 CPU/MEM shelf to ENB.
Set the MAINT/NORM switch on CPU 0 to NORM and press the
MANT/INI button associated with CPU 1.
Note: The system transfers to CPU 1 when performing this step. If
an INI does not occur within 30 seconds, press the MAN INI button
again.
20 Load overlay program 35.
Ensure that the SBE, CMA and MEM circuit packs for CPU 1 are
enabled and the system is operating.