19 Commissioning

In this chapter

19.1 Overview: Commissioning

19.2 Precautions when commissioning

19.3 Checklist before commissioning

FDA125A5VEB
Split system air conditioners
4P495031-1B – 2022.10
NOTICE
General commissioning checklist. Next to the commissioning instructions in this
chapter, a general commissioning checklist is also available on the Daikin Business
Portal (authentication required).
The general commissioning checklist is complementary to the instructions in this
chapter and can be used as a guideline and reporting template during commissioning
and hand-over to the user.
19.1
Overview: Commissioning ......................................................................................................................................................
19.2
Precautions when commissioning..........................................................................................................................................
19.3
Checklist before commissioning.............................................................................................................................................
19.4
To perform a test run .............................................................................................................................................................
This chapter describes what you have to do and know to commission the system
after it is installed.
Typical workflow
Commissioning typically consists of the following stages:
1
Checking the "Checklist before commissioning".
2
Performing a test run for the system.
INFORMATION
During the first running period of the unit, the required power may be higher than
stated on the nameplate of the unit. This phenomenon is caused by the compressor,
that needs a continuous run time of 50 hours before reaching smooth operation and
stable power consumption.
NOTICE
ALWAYS operate the unit with thermistors and/or pressure sensors/switches. If NOT,
burning of the compressor might be the result.
NOTICE
ALWAYS complete the refrigerant piping of the unit before operating. If NOT, the
compressor will break.
1 After the installation of the unit, check the items listed below.
2 Close the unit.
3 Power up the unit.