8-1. LIFT LINKAGE

8-1.1. Removal
1.
Lift complete truck to height sufficient to permit
access to lift linkage under forks. Provide blocking
under frame (8,
Figure
forks.
2.
Turn off the key switch (20,
emergency disconnect (17).
R6744
BL-E30-0515 - 07-27-2016
SECTION 8

ELEVATION SYSTEM SERVICING

8-1) and at tips of the
Figure
12-18) and
Figure 8-1 Frame
3.
Remove pins (10,
Figure
(11).
4.
Remove clips (3) from each side of frame (8).
Support link assembly and remove shaft (9).
5.
Remove pins (7) and remove shafts (6).
6.
Lower link assembly to the floor.
8-1) and remove shafts
8-1