30. Using the 5-1/2" Torq screws, screw through the roof panel to
secure to the top of the walls. Secure the roof panel at the front of
the sauna and ensure the side overhang in the back of the sauna is
the same as the front. Secure roof to back wall and then side walls.
31. Once the roof panels are secured, remove the guide strips at the
front so trim can be installed later.
32. Nail fascia trim to the exterior edge of roof starting with the back
edge. Next the two side edges, and lastly the front edge. The fascia
top should be flush with the top of the roof panel.
33. Install eve trim under the overhanging fascia on front and back of
sauna only. The front side eve trim is flush to the left and right-side
fascia. The back trim is flush to the left and right-side fascia.
34. Install the left and right-side eve trim so it is flush to the back
side trim and front side trim.
35. Install exterior cove trim to the back wall so it is flush to the left
and right edges of the wall.
36. Install exterior cove trim to left and right-side walls so it is flush
to back side cove and the edge of the front wall.
37. Install exterior cove trim to front wall so it lays flush to left and
right-side cove.
38. Install the roofing felt on the roof panel using a roofing stapler.
Start from the low side of the room, working towards the high
side. Overlap the paper a minimum of 2".
Trim roofing felt to be flush with the edges of
the roof panels.
71-0156