23. Install a 3" Torq screw into each access opening to secure the walls
to the base plate and floor
24. Install an access board into each opening. Secure with Brad nails.
Note: Electrical access or other labeled access boards are
intentionally left uninstalled. Do not install panels until electrical
components have been installed and assessed by a licensed
electrician.
Roof Panel Installation
Note: Number of roofing panels will vary
depending on the roof size.
25. Using two people, carry the first roof panel over to the sauna,
carefully feed the roof panel into place without scratching the
panels. When in position, it will rest on the top plate.
26. The guide strip will align exterior of the high side wall panel until
final placement is set and secured.
27. Make sure the first panel is aligned using the guide strip at the
front end of the panel. Continue placing remaining panels, make
sure all panels are centered with even overhang. Approximately 8
inches overhang on right and left side.
28. The tongue and groove of the inner ceiling should fit together
snug.
*A rubber malett may be needed to aceive a snug fit.
29. Secure roof panels together using a 3" Torq screw. Drive screw in
at a 45-degree angle connecting the two panels together at the
seam to make one large panel. Complete this step at both front
and back of roof panels.
71-0156
Rev. 03
Page 8
4215-136
10/21/2022