Installing The Cartridge Group; Fig. 34: Installing O-Rings; Fig. 35: Installing The Cartridge Group 1 - ABB PT004165 Operation Manual

Table of Contents

Advertisement

Operation Manual / Power2 850-M / High-pressure stage
9 Disassembly and assembly / 9.11 Installing the cartridge group
9.11

Installing the cartridge group

Fig. 34: Installing O-rings
Fit new O-rings (42017 / 42018).
u
Fig. 35: Installing the cartridge group 1
1. Clean slots for lamellar rings (64001) and fit new lamellar rings. Arrange joints so that
they are offset by 180°.
2. Fit bracket (90030) and plates (90031).
3. Fit lifting gear to swivel lifting eye (90657).
4. Lift cartridge group and carefully move in.