11. Dismount the permeate hose
and lead it to drain.
12. Reconnect power to the plant.
13. The plant will now be operat-
ing. Let the plant flush this
way for 20 or 30 minutes.
14. Adjust the outlet valve V02
and the recirculation valve
V01, see section regarding
commissioning of plant.
15. Check
that
the
pressure of the plant, dis-
played on the manometer, is
14.5 to 16 bar which is the
normal operating pressure.
16. Check that the water quality is
< 50 μS/cm.
Write in the operating journal:
1. Date of replacement of
membranes
2. New capacity of plant
3. Water quality (µS/cm)
operating
4. Plant operating pressure
5. Raw water pressure
6. Raw water temperature
UK
17

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the PERMAQ COMPACT 41 and is the answer not in the manual?

Questions and answers

Table of Contents