  • Page 1 Installation and Operating Manual ® BWT PERMAQ PRO 2510-2540 Reverse Osmosis Plant...
  • Page 3: Table Of Contents

    LIST OF CONTENTS GENERAL EXPLANATION OF WORDS PLACING OF PLANT WATER QUALITY WATER CONNECTIONS ELECTRICAL CONNECTIONS START-UP OF PLANT 7.1 Adjustment of outlet amount 7.2 Adjustment of the Recirculation Amount OPERATING MANUAL FOR OPERATOR MENU 8.1.1 Information in menu: 8.1.2 Functions in menu: 8.2 Operation 8.2.1...
  • Page 4 13. VARIOUS ENCLOSURES 13.1 P & I Diagram 13.2 Layout Drawing 13.3 Operating journal 13.4 List of components and Spare parts for the BWT PERMAQ® PRO 2500 series 19 13.5 Spare parts drawing 13.6 Declaration of Conformity 13.7 Circuit diagram...
  • Page 5: General

    GENERAL have to be refitted. quality. This user guide applies to the BWT PERMAQ® PRO 2500 The BWT PERMAQ® PRO 2500 Membranes Is the plant filter series of total desalination plants. plant is designed for minimum which by high...
  • Page 6: Water Quality

    1" flexible pressure hoses.  KMnO max.: 10 mg/l possibly a reservoir tank (option). BWT sell complete assembly kits Maximum temperature:25 C. for the BWT PERMAQ® PRO You must expect 1000 mm extra Note! The plant has been 2500- series.
  • Page 7: Electrical Connections

    Permeate Drainage The electrical connection to the Plant capacity amount l/h BWT PERMAQ® PRO 2500 Completely open the outlet valve type plant must be as follows: V4. (See diagram of principle). 75 % Completely close the recirculation 2500...
  • Page 8: Operating Manual For Operator Menu

    Press Alarm setting the stated intervals In case of deviations you may contact In alarm setting you can make BWT’s service department. selections for set point and delay of alarms.  if the capacity has...
  • Page 9: Functions In Operation

    8.2.2 Functions in Opr. Setting 2 Operating status of valves and Operation: pumps. Press OFF-ON RO: Pumps change colour (black = stopped, white = operating) For start/stop of plant. Valves change colour (black = Press OFF-ON FLUSH: closed, white = open.) For start/stop flush of plant.
  • Page 10: Alarm Setting

    ENT. for scrolling up and down in the alarm display. 8.10.3 Password: Password will be informed if you Date/time contact BWT A/S Tel.: +45 43600500 Service Department 8.7.1 Information in Plant MAINTENANCE type: AND TROUBLE- RO Type and selection of option.
  • Page 11: Trouble-Shooting

    following must be checked 9.2.1 The plant capacity 12. Replace defective/buzzing regularly: has decreased switches and relays If the operating conditions of the This can be read on the flow Note! If the plant has to be plant are changed compared to meter (FI1) while the RO plant is taken out of operation for a long the settings on the day of start-up,...
  • Page 12: 9.2.3 Alarms

    Write down in the day. After rinsing the outlet REPLACEMENT operating journal: amount must be readjusted, see OF MEMBRANES paragraph for Start-up of the Read this paragraph before 13. Date of replacement of Plant. membranes. dismounting/replacing the plant membranes. 14. New capacity of the plant Check: (flow meter FI1 and FI2) if raw water comes in connection...
  • Page 13: Cip-Cleaning Of Membranes (Option)

    10. 21. Lift the dosing control until increased pressure loss across the BWT CIP 4 is sold by BWT Item the control signal disappears, membrane and thus a drop in and then lower it just enough No.: 70 19 57 020...
  • Page 14 CIP pump P2 by pressing "stop" “Start-up of plant”. on the panel front. Start by cleaning with BWT CIP Let the membranes soak for about 10 and then clean with BWT CIP 4. Always follow the safety 1 hour.
  • Page 15: Various Enclosures

    VARIOUS ENCLOSURES 13.1 P & I diagram 13.2 Lay-out drawing 13.3 Operating journal 13.4 List of components and spare parts for RO 13.5 Spare parts drawing 13.6 Declaration of Conformity 13.7 Circuit diagram...
  • Page 16: P & I Diagram

    13.1 P & I Diagram...
  • Page 17: Layout Drawing

    13.2 Layout Drawing...
  • Page 18: Operating Journal

    13.3 Operating journal...
  • Page 19: List Of Components And Spare Parts For The Bwt Permaq® Pro 2500 Series

    13.4 List of components and Spare parts for the BWT PERMAQ® PRO 2500 series Recommended Recommended Item No. Item text – RO plant Item No. replacement spare parts frequency (month) ¾” Needle valve with counter nuts 200731006 1” Ball valve 200742008 ¼”...
  • Page 20 14 mm collector 454097014 48-60 14 mm elbow 454090014 48-60 14 mm T-piece 454095014 48-60 4” end plate 451404113 48-60 4” end plate 451404112 48-60 Lip ring for 4” membrane 6-12 451404208 48-60 * Contact your local BWT dealer for detailed information.
  • Page 21: Spare Parts Drawing

    13.5 Spare parts drawing...
  • Page 22: Declaration Of Conformity

    +45 43 600 500 - fax: +45 43 600 900 bwt@bwt.dk - www.bwt.dk Herewith declares that: BWT PERMAQ® Pro 2510, 2520, 2530, 2540 is in conformity with the provisions of the Machinery Directive (Directive 2006/42/EC) is in conformity with the provisions of the following other EC directives...
  • Page 23: Circuit Diagram

    13.7 Circuit diagram...
  • Page 49 Notes ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________...
  • Page 50 Notes ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________...
  • Page 51 Notes ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________ ________________________________________________________________________________...
  • Page 52 Fax: +33 1 4922 45 45 E-Mail: office@bwt.at E-Mail: bwt@bwt.de E-Mail: info@cillichemie.com E-Mail: bwt@bwt.fr BWT Belgium NM. BWE Česká Republika s.r.o. BWT Polska Sp. z o.o. BWT Hungária Kft. Leuvensesteenweg 633 Lipovo 196 -Cestlice ul. Polczyhska 116 Keleti út. 7. B-1930 Zaventem CZ-251 01 Říčany...

Table of Contents