PERMAQ ® mation about the correct installa- possible. Compact 51 plant tion and operation of the BWT With its compact and finished de- and which must be PERMAQ ® Compact 51. sign, your BWT PERMAQ ®...
Open the outlet valve (B-Figure plant retention rate of 98 % applies capacity for every degree under 3) complete and close the recir- by 75% recovery. Contact BWT or 10 °C. culation valve (D-Figure 3). If e.g. the raw-water temp. is 8 °C, the supplier of your plant to decide ®...
FUNCTIONS 160 l/h, i.e. 151 l/h. At the same minutes). Check that the level time make sure that the pressure switch (H-Figure 3) automatically The BWT PERMAQ ® Compact 51 on the manometer (E-Figure 3) stops the plant when the reservoir plant is equipped with a control does not exceed 15 bar incl.
MAINTENANCE AND TROUBLE-SHOOTING Maintenance The BWT PERMAQ ® Compact 51 plant is produced and designed for a minimum of servicing and maintenance. However, there are certain functions which should be checked regularly. Maintenance intervals should be per- formed once a week – read section 13.5 Operating Journal.
Troubleshooting This section deals with the problems that may arise on the plant. 9.2.1 The plant capacity has dropped 9.2.2 The quality of the treated water is higher than 20 µS/cm...
9.2.10 Survey of alarm condition LED function: In normal operation the LED’s are lit corresponding to the components they represent. “Re-start ALARM” on TP-pump: (Nothing is working - permanent Section 9.2.8 condition) ALARM - Too high water level: (Nothing is working - permanent Section 9.2.6 condition) Restore raw water pres-...
It is possible to change the various time settings for Start, Stop and Alarm, plus delayed start-up of pumps. Use of DIP-switch: No. 1 High-pressure pump No. 2 Transport pump ® No. 3 Selection of BWT PERMAQ Compact 51 model No. 4-6 Transport pump TECHNICAL SPECIFICATION 10.1 Technical specifications ® BWT PERMAQ Compact...
BWT PERMAQ ® every operating period. high-pressure pump. The per- Compact 51 from BWT and fill If the membranes are very meate (desalinated water) is in 25 litres of warm raw water blocked due to too late clean- then led to consumption and can 40°C.
Write in the operating journal: Figure 3) back into the reservoir that the V-cup seal has to be tank. placed at the top when the The plant is ready for normal membrane is fitted inside the 1. Date of replacement of operation.
NO, the problem does not concerns the plant or the installation The plant - we mean only the part of the whole installation which was delivered by BWT (i.e only the plant). The installation - we mean the piping etc. leading to the plant.
13.5 Operating Journal Maintenance intervals should be performed once a week. Replacement frequency of wearing parts shown in ® section 13.6 Spare Parts List BWT PERMAQ Compact 51.
Need help?