2.2.2 Install the 1 RU Distribution Shelf
Figure 2-7
2.2.2.2 Install the DC Power Cabling (Optional)
If the system is equipped with the 1 RU Distribution Shelf, follow the instructions below. For systems
without the 1 RU Distribution Shelf, skip this procedure and go to the
procedure on page
Locate the four 6AWG (16mm²) power cables provided at the rear of the system shelf (on top of the
Step 1
system shelf in preinstalled systems). These are terminated with Anderson Powerpole™ Connectors (to
install these connectors, remove the heat shrink from the ends of the connector).
Connect to the appropriate connection points on the 1RU Distribution Shelf labeled load (-48V) and
Step 2
return (RETURN)
Note
Cisco AC/DC Power System User Guide, R1.0
2-8
1 RU Distribution Shelf Alarm Cabling
2-9.
(Figure
2-8).
Anderson Powerpole™ Connectors are keyed and can only be inserted one way. If the connector
does not insert easily into the mount, make certain that the connector is being inserted with the
key side up.
Chapter 2
System Installation
"2.2.3 Install the Ground Cable"
May 2006