Annual Maintenance Procedures
1
Remove the boom end cover from the pivot
end of the boom.
1 boom end cover
2 side access covers
3 cable ends (located underneath the boom)
118
2
Remove the retaining fasteners from the
access covers located on the side of the boom
at the platform end of the machine. Remove
the covers.
3
Visually inspect the cables and components
through the inspection holes for the following:
• Frayed or broken wire strands
• Kinks or crushed cables
• Corrosion
• Paint or foreign materials on the cable
• Split or cracked cable ends
• Cables are on all sheaves
• Cables have equal tension
• Cables at end of adjustment range
• Broken or damaged sheaves
• Unusual or excessive wear
• All fasteners in place and secure
Note: A flashlight and inspection mirror may be
necessary to thoroughly inspect the above items,
or an endoscope inspection camera.
Note: Refer to Maintenance Procedure P12-2,
Cable Replacement Criteria.
Note: If required, the extend or retract cables must
be replaced as a set.
Note: If the boom extend or retract cables are
replaced, quarterly maintenance inspections must
be performed for the first year.
4
At the pivot end of the boom, visually inspect
for the following:
• The red locking bracket is securely installed
over the cable adjustment bolts.
S
®
Booms • Z
®
Booms
October 2018
Part No. 1268489GT