8. Install Overhead Beam
A. Install cylinder mounts (uprights) using 2ea 1/2" x 1-3/4" bolts, washers & nuts on each end, (Figs.
7a, 7b, 7c). NOTE: ENSURE OVERHEAD LIMIT SWITCH ASSEMBLY IS ON THE MAIN SIDE
COLUMN SIDE.
Fig. 7a
9. Anchoring Off Side Column
A. Using a level, check the alignment and
plumbness of the entire structure. Plumb the off
side column both side to side and front to back.
B. The base of the column may vary from the
preliminary layout, as it is more important that
the column be perpendicular to the floor and
parallel to the other column.
C. Install the anchor bolts and shim the base as
described in Step #6
Position Overhead Limit Switch
Assembly on same side as power unit.
Fig. 7c