SECTION 7 - GENERAL SPECIFICATIONS & OPERATOR MAINTENANCE
1. Start all nuts by hand to prevent cross threading. DO NOT
use a lubricant on threads or nuts.
2. Tighten nuts in the following sequence:
7-36
3. The tightening of the nuts should be done in stages. Follow-
ing the recommended sequence, tighten nuts per wheel
torque chart.
Table 7-20. Wheel Torque Chart
TORQUE SEQUENCE
1st Stage
2nd Stage
45 ft. lbs.
100 ft. lbs.
(60 Nm)
(140 Nm)
4. Wheel nuts should be torqued before first road use and after
each wheel removal. Check and torque every 3 months or
150 hours of operation.
3rd Stage
180 ft. lbs.
(252 Nm)
3121170