5.7

Prepare for commissioning

1. Tell the owner that the EVSE is ready for commissioning.
2. Make sure that the site agrees with these requirements:
3. Make sure that these data are available:
BCM.S1102.0-EN | 001
Danger:
Hazardous voltage
Do not commission the EVSE. Only a service engineer of the
manufacturer is qualified to commission the EVSE.
The EVSE is installed.
AC input power is available from the grid provider.
You are present during the commissioning, for assistance and to energize
the power to the EVSE on the power distribution board.
Internet access is available, through 2G/3G/4G or through a wired Ethernet
connection.
An EV must be available with a compatible connection. If the EVSE has more
than one connection type, an EV of each type must be available.
The site operator or owner is available to receive instructions from the
service engineer of the manufacturer.
Contact data of the contact person on site
Address of the EVSE
Site name
Exact location of the EVSE: longitude and latitude. If there are more EVSEs
on one location, make sure that the coordinates are slightly different (at
least 0.0001 degree) so that the EVSEs are not at the same location on the
map.
Specification of the external fuse at the power distribution board
Date that the installation is done
Special remarks, for example to decline the authorization for the service
engineer of the manufacturer to take photos
Photo of the surroundings of the EVSE
Installation
33

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Terra 124Terra 184

Table of Contents