Black Start
To black start the system, use the following guidelines:
1.
Connect the communication cable between the BMS and the PCS, making sure to set the correct
batter manufacturer settings.
2.
Turn on the BMS power.
The BMS establishes a communication connection with the PCS, and the battery outputs to the HV DC.
Once DC input from the battery to the PCS is established, operation mode is initiated. The PCS is
then activated and a micro grid is established, completing the black start process.
Installation Manual
Figure 50.
CNJ5 Pin Assignment