Delta PCS100 Installation Manual page 20

Power conditioning system
Hide thumbs Also See for PCS100:
Table of Contents

Advertisement

3. Risk to system reliability due to ground fault.
To prevent possible ground fault risks, equip the corresponding GFD equipment. The battery warranty
may be null and void if the GFD equipment is not equipped.
WARNING!
!
The weight of the PCS is distributed on a small surface of the floor. It is necessary to verify
the floor load-bearing capacity.
All service and maintenance personnel must be trained in normal as well as emergency procedures.
Chain Hoist Installation
The dimensions and weights specified must be taken into consideration when mounting the
PCS100. All lifting equipment and lifting components (hooks, bolts, lifts, slings, chains, etc.) must
be properly sized and rated to safely lift and hold the weight of the PCS100 during the mounting
process.
CAUTION!
!
T
PCS100,
O MOVE THE
CAUTION!
!
I
F USING LIFTING LUGS
TO THE HOOD AND BE SURE TO USE A MINIMUM OF FOUR STRAPS OF SUFFICIENT LENGTH
Installation Manual
USE LIFTING EQUIPMENT THAT HAS APPROPRIATELY RATED LIFT CAPACITY
,
BE SURE THE SPREADER BAR IS SUFFICIENTLY LONG TO PREVENT DAMAGE
16
Installation
.
.