Delta PCS100 Installation Manual page 27

Power conditioning system
Hide thumbs Also See for PCS100:
Table of Contents

Advertisement

15. Connect the hoist to the eye bolts on the cabinet. Make sure the load is secured before making
any attempt to move it. The recommended diagonal length of the sling is 2 to 2.5 m (6.56 to 8.2
ft.).
16. Follow the hoist manufacturer's guidelines on moving the load as described in the
manufacturer's operation manual.
WARNING!
!
Check on Sling Angle. Ensure that the sling angle is always greater than 45º and preferably
greater than 60º . When the horizontal distance between the attachment points on the load is
less than the length of the shortest sling leg, then the angle is greater than 60º and generally
safe.
17. Once the PCS is place in its final installation site, secure the PCS to the site as described in
"Securing a Cabinet in a Final Location" on page 28.
18. Remove the hoist.
19. Once the cabinet is secured to the location, install the top cover, see "Securing a Cabinet in a
Final Location" on page 28.
Installation Manual
Figure 23. Eye Bolts Locations
23
Installation

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents