5. The flexible lines must not be kinked when fitted.
6. Install a shut off valve if a fill/drainage connection is used.
7. Fill and pressurise the system to 3 bar to test the installation for leaks prior to connecting to the Baxi
Ambiflo™ Heat Pump.
NOTE: Baxi strongly recommend that all the system pipework is flushed at the isolation valves prior to
connecting the Baxi Ambiflo™ flexible lines to prevent blockage of the Heat Exchanger and In-line Strainer.
8. The anti-vibration pads and in-liner strainer are supplied inside the heat pump front panel. Please
ensure these parts are removed prior to commencing this installation. See Fig. 18 for access to the kit.
Fig. 18
5.5 Initial Preparation (Electrical Connection Points)
To remove side panel (A) :