A+ SERVER 2122TG-H6IBQRF/H6RF USER'S MANUAL

Standard Chassis Installation

Stability hazard. The rack stabilizing mechanism must be in place, or the rack
must be bolted to the floor before you slide the unit out for servicing. Failure
to stabilize the rack can cause the rack to tip over.
Installing the Chassis into a Rack (Figure 2-6)
1. Confirm that the inner rails are properly installed on the chassis.
2. Confirm that the outer rails are correctly installed on the rack.
3. Pull the middle rail out from the front of the outer rail and make sure that the
ball-bearing shuttle is at the front locking position of the middle rail.
4. Align the chassis inner rails with the front of the middle rails.
5. Slide the inner rails on the chassis into the middle rails, keeping the pressure
even on both sides, until the locking tab of the inner rail clicks into the front of
the middle rail, locking the chassis into the fully extended position.
6. Depress the locking tabs of both sides at the same time and push the chassis
all the way into the rear of the rack.
7. If necessary for security purposes, use screws to secure the chassis handles
to the front of the rack.
Ball-Bearing Shuttle
Warning: Do not pick up the server with the front handles. They are designed
to pull the system from a rack only.
Figure 2-6. Installing into a Rack
2-8