Commissioning
76
6.10
Commissioning with the handheld terminal
Field Communicator 375/FC375
The steps of the commissioning procedure are the same as with a FOUNDATION Fieldbus
configuration tool (→ Chap. 6.9).
The blocks should be parametrized in the following order:
• the RESOURCE BLOCK
• the SENSOR BLOCK
(the "basic setup" method can be used for this, see chapter "basic setup")
• the ANALOG INPUT BLOCKS
Levelflex M FMP43 with FOUNDATION Fieldbus