Three Phase Power Connections

Figure 2. Three Phase Control Box Power Connections
MOTORIZED
TROLLEY
PLUG
POWER
CABLE
GLAND
1. Remove the control box cover.
2. Insert the power supply cable through the cable gland.
3. Connect phases L1, L2, L3, PE (GROUND) to mainline contactor K10.
4. Tighten the terminal screws
5. Tighten the cable gland or connector to secure the cable.
6. Connect push button assembly to X23.
7. Connect motorized trolley (optional).
8. Close the control enclosure cover.
This document and the information contained herein, is the exclusive property of R&M Materials Handling, Inc., and represents a non-public, confidential and proprietary trade secret that
may not be reproduced, disclosed to third parties, altered or otherwise employed in any manner whatsoever without the express written consent of R&M Materials Handling, Inc.
Copyright © (2010) R&M Materials Handling, Inc. All rights reserved.
L1
L2
PE
L3
PUSHBUTTON
PLUG
CONNECTION
X23
12/89

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents