11. Maintenance

11.3 Maintenance Program Summary

P71 to P84
Free programming locations
P43
Deodorizing:
The following maintenance programs are installed in the M12/M15/M18:
P44
Short drying
P45
Distillation maintenance
P46
Filter 1 filter maintenance
P47
Filter 2 filter maintenance
P48
Adsorber maintenance (only
on PERC machines with
Slimsorba)
P49
Multi-maintenance 1
P50
Multi-maintenance 2
P51
Fill tanks
P52
Prepare stock solution
P53
Drain extraction tank
P54
Rinse the water separator
P55
Pumping out the distillation
residue
P56
From tank 1 to cage
P57
From tank 2 to cage
P58
From tank 3 to cage
72
Attention: Always select this if the loading door cannot
be opened.
For afterdrying
Still stripping or program sequence "emission-free
still rake out (see Point 11.5.7)
Extraction of the filter disc, followed by still
stripping.
Extraction of the filter disc, followed by still
stripping.
For desorption of the Slimsorba at times other than
during the cleaning cycles. The program has two
phases: desorption and carbon cool-down.
Combination of filter maintenance for filter 1,
Slimsorba maintenance, water separator
maintenance and distillation maintenance.
Combination of tank maintenance for tanks 1 + 2 +
3, spray nozzle rinsing and flushing of the drum
back plate
Fill the clean tank and then overflow into the work
tank and further into tank 3
Addition of drycleaning detergent into the solvent
from the work tank and tank 3 through a recipient
tank in the button trap.
Pump the extraction tank out to distillation
Automatic cleaning of the water separator
(only with emission-free still rake out system)
For cleaning the work tank
For cleaning the clean tank
For cleaning the extra tank
11.
11.3
M12/M15/M18

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

M15M18

Table of Contents