Start-up Operation

5.1

Start-up

Before beginning start-up, the wiring of the Controller (including all field devices) must be completely terminated!
After switching the power supply "ON" and the end of the Power On Time, then the Controller is ready for use.
The electrochemical sensor needs a warm up time of 1 hour to reach its highest accuracy.
The Controller is delivered with standard parameters and stages/set points. The assignment of the relays to the
individual stages can occur at start-up unless arrangements have been made with the factory for programming. All
other parameters are to be examined and adapted to the local conditions.
Polygard® is a registered trademark of MSR
Customer Services (858) 578-7887 & (888) GO INTEC
INTEC Controls, 12700 Stowe Dr., Suite 100, Poway, CA 92064
Fax (858) 578-4633 & (888) FX INTEC
www.inteccontrols.com
Page 28
Specification subject to change without notice.
Printed in USA 131119
MGC2-12

Advertisement

Table of Contents
loading

Table of Contents