ADS1271EVM Hardware Details
5
ADS1271EVM Hardware Details
The ADS1271EVM is designed to easily interface with multiple control platforms. Dual-row, header/socket
combinations of J1 and J2 allow connection to external circuitry for evaluation and debug.
5.1
Jumpers and Switches
The jumpers and switches functions are shown below in
Jumper/Switch
Functions
J1
Analog inputs/external reference (primary)
J2
Digital Interface signals
J3
Power
J4
Analog inputs/external reference (aux)
J5
Analog inputs/external reference (aux)
J6
Power
J7
Format/Mode Selection
S1
Analog input to buffer
S2
Analog input to buffer
S3
U7 Reference selector
S4
U7 Analog Input selector
S5
U8 Reference selector
S6
U8 Analog Input selector
S7
Interface selector
5.2
Analog Connections
5.2.1
Analog Interface, J1, J4, and J5
The ADS1271EVM features several analog input options. Signals can be routed directly to the converters
or can pass through the onboard buffer amplifiers (U5, U6). Signals can be applied to the board through
the standard modular EVM analog connector (J1) or brought in through the auxiliary input connectors (J4,
J5). A set of switches selects which analog connector source is used and whether the buffer amplifiers are
in the signal path. These switches enable several configurations for evaluation. Switch operation and
analog path configuration are described in
For maximum flexibility, the ADS1271EVM is designed for easy interfacing to multiple analog sources.
Samtec part numbers SSW-110-22-F-D-VS-K and TSM-110-01-T-DV-P provide a convenient 10-pin, dual-
row, header/socket combination at J1. This header/socket provides access to the analog input pins of the
ADS1271.
Pin Number
J1.1
J1.2
J1.3
J1.4
J1.5
J1.6
J1.7
8
ADS1271EVM and ADS1271EVM-PDK User's Guide
Table 4. Jumper and Switch Descriptions
Section
Table 5. Analog Interface Pinout (J1)
Signal
Description
AIN0N
ADS1271 (U7) AINN
AIN0P
ADS1271 (U7) AINP
AIN1N
ADS1271 (U8) AINN
AIN1P
ADS1271 (U8) AINP
Unused
Unused
Unused
Copyright © 2004–2014, Texas Instruments Incorporated
Table 4
Descriptions
Primary analog input/external reference connectors (from
MMB0)
Serial Interface and GPIO signals (from MMB0)
Power supply connections (from MMB0)
Auxiliary analog input/eternal reference connector for U7
Auxiliary analog input/eternal reference connector for U7
Power selection and supply monitoring
Connection of Format and Mode controls to ADCs
Selection of which analog signal header to connect to buffer,
U5
Selection of which analog signal header to connect to buffer,
U6
Select source of reference for U7
Select source of analog input for U7
Select source of reference for U8
Select source of analog input for U8
Select interface type (FORMAT)
5.2.2,
Table 6
, and
Table
SBAU107C – November 2004 – Revised November 2014
www.ti.com
7.
Submit Documentation Feedback
Need help?
Do you have a question about the ADS1271EVM-PDK and is the answer not in the manual?
Questions and answers