ADS8555EVM Operation
6.3 Modifying Hardware and Using Software to Evaluate Other Devices in the Family
The ADS8555 is part of a family of related devices. This EVM hardware and software support the entire family
because all the devices are pin-for-pin compatible. The
following procedure shows how to modify the hardware and software to evaluate the other devices in this family.
1. Desolder the ADS8555 and replace this device with the device you want to evaluate.
2. Enable the EEPROM for writing. This process is done by changing switch S2 to the WR_EN (top) position
using tweezers.
Figure 6-3
3. Connect the EVM and start the GUI as described in
4. Under the Tools menu in
is currently installed. When this procedure is successfully completed, the status bar at the top of the software
updates according to the device installed on the hardware.
DEVICE
RESOLUTION
ADS8555
16
ADS8556
16
ADS8557
14
ADS8558
12
3. After pressing ^load
EEPROM_ it will take a few
minutes to load the EEPROM.
Figure 6-4. Configure EEPROM and Software for the New Device
14
ADS8555EVM-PDK Evaluation Module
details this process.
Figure
6-4, select Load EEPROM to load the EEPROM according to the device that
Table 6-2. Compatible Devices
PARALLEL
SERIAL DATA
DATA RATE
RATE
630
450
630
450
670
470
730
500
Use tweezers to change
position of switch S1
^WR_EN_ as shown to
allow the EPROM write
operation.
Figure 6-3. Enable EEPROM for Writing
1. On the ^tools_ menu
select ^load EEPROM_
Copyright © 2021 Texas Instruments Incorporated
Table 6-2
lists other compatible devices in the family. The
Figure
6-2.
OTHER FEATURE
Does not have partial power-down mode
—
—
—
2. Under ^Supported Devices_
select the desired devices and
press ^Load EEPROM_X
4. The top of the status bar on the
software will indicate what the EVM
connected has been updated to.
SLAU298A – NOVEMBER 2009 – REVISED MAY 2021
www.ti.com
Submit Document Feedback
Need help?
Do you have a question about the ADS8555EVM-PDK and is the answer not in the manual?
Questions and answers