Hardware Detection - Inspur i24 Server Acceptance Manual

Table of Contents

Advertisement

Expected result
Description
Table 1- 5 PSU Backup Function
Item
Objective
Prerequisites
Procedure
Expected result
Description

1.1.4 Hardware Detection

Table 1- 6 Hardware Detection
Item
The server is operating properly during the test.
None
Content
To verify the PSU backup function.
The structure of the mainboard and hard disk backplane is
intact.
1.
Insert two PSUs into the server.
2.
Connect power cables to the PSUs and wait 10 seconds
until the server is powered on.
3.
Check that the power status indicators on the PSUs are
steady on.
4.
Remove the power cable from the first PSU, and remove
the first PSU from the slot. Check that the other PSU and
the server are operating properly.
5.
Insert the first PSU into the slot. Check that the power
status indicator is steady on.
6.
Remove the power cable from the second PSU, and
remove the second PSU from the slot. Check that the
other PSU and the server are operating properly.
The server is operating properly during the test.
None
Content
Inspur proprietary and confidential information
Copyright © Inspur Electronic Information Industry Co., Ltd.
7