5 . Insert the stripped PE, N and L1 wires into the matching terminals (see fi gure 35 ).
The L1 cable must always be connected to the grey terminal block.
NOTICE
To make optimal use of the available power of 3-phase connections, use phase rotation when installing multiple charge
points. There are three possible phase rotations (see fi gures 36 , 37 and 38 ).
6 CAUTION
If phase rotation is not correctly applied, Dynamic Power Sharing will not work correctly and could result in overloading
the grid connection.
All charge points must be installed and connected in accordance to the installation procedure of this manual.
Always apply phase rotation at the bottom of the kWh meter.
Option 1
L1
L2
L3
Q
6 . Insert the stripped L2 and L3 wires into the bottom of the kWh meter. Apply a torque of 2.4 Nm.
7 . Write down the applied phase rotation on the installation form on the back of the Quick Installation Guide. See
chapter 7 . 1 . Confi guration.
Installation manual – NewMotion Business Pro & Lite 2.1 / 2.2 - 091NMEN13
m
Option 2
L3
L1
L2
W
Option 3
L2
L3
L1
E