* The installer must select a suitable MCB to match the current setting of the charge point, taking into
account MCB manufacturer specifications and EV-Ready guidelines;
** The electrician is responsible to select a suitable RCD to match the local rules and regulations. Please
note that these may be different from the international rules and regulations.
The charge point can be limited between 6 A and 32 A, as described in chapter 7.3. Switching on the product.
NOTICE

5.2.6. Charge point mounting

For wall mounting, use 5 × coach screws (6.3 × 70 mm), washers and plugs.
For pole mounting on a concrete base, use fill sand to cover the hole of the concrete base for optimal stability.

5.2.7. Installation tools and materials

Make sure to have a basic electricians toolkit when installing a NewMotion charge point.
Icon
Description
Cabled ethernet connection.
Data cable tester (RJ45).
Ethernet connection - incoming data such as a Business Pro, upstream Business Lite or (mobile) router.
Ethernet connection - outgoing data such as a downstream Business Lite or DPM for Business module.
Fill sand.
Cellular signal strength measuring tool.
Pencil.
Plug for mounting in wall (if applicable).
Power drill and drill bits.
Installation manual – NewMotion Business Pro & Lite 2.1 / 2.2 - 091NMEN13