Electrical Connection; Power Cable - newmotion Business Pro 2.2 Installation Manual

Table of Contents

Advertisement

M8 × 12 mm
14 . Secure the casing to the pole using 4 provided M8 × 12 mm bolts and washers (see fi gure 33 ).
Secure the supplied earthing wire between the casing and the bottom right screw.
NOTICE
5 . 5 .

Electrical connection

5 . 5 . 1 . Power cable

For the next four steps see fi gure 34 .
1 . Ensure you have ± 15 cm of free power cable, measured from the inlet grommet.
2 . Remove ± 10 cm of the outer insulation from the power cable.
3 . Strip ± 1 cm of the insulation from the fi ve wires.
4 . Insert the earthing wire into the earth terminal.
Installation manual – NewMotion Business Pro & Lite 2.1 / 2.2 - 091NMEN13
± 10 mm
± 100 mm
b
n
L1
L2
L3
N
PE
25
EN