2.6.5. Fully de-energizing AC power (hard-wired machines)

Contact the customer's site supervisor before attempting this procedure. Only
the customer's authorized site maintenance personnel are permitted to shut
off the site AC power.
At some customer sites, the Sure Sort is hard-wired to a dedicated AC main
disconnect switch located near the machine. To safely de-energize the Sure
Sort AC Distribution enclosure, the incoming power must be shut off by turning
off and locking out the customer's main disconnect switch.
An Authorized Employee or qualified electrician must proceed as follows:
1. Complete all steps under
page
72.
2. Customer's site maintenance personnel only: shut off the main AC
disconnect switch and install a Lockout-Tagout device (Figure 2-18).
Figure 2-18: Example- AC main disconnect with Lockout/Tagout
Safety
WARNING
"LOTO - Machine maintenance and repair" on
Sure Sort™ Operator Manual
OPEX Corporation
77

Hide quick links:

Advertisement

loading
Need help?

Need help?

Do you have a question about the Sure Sort and is the answer not in the manual?

Questions and answers