Assembly and installation
Moving the Suction Lance and Power Line to the Left-Hand Side of the Housing
1.
Remove the bonnet.
2.
Remove the suction line from the dosing pump.
3.
Disconnect the suction lance connection cable in the electronics control box.
4.
Loosen the hose clamp.
5.
Unscrew the union nut from the suction lance.
6.
Pull the suction lance together with the suction line and connection cable out of the
housing.
7.
Pull the mains cable gland out of the holder.
8.
Pull the mains cable bushing together with the mains cable back into the housing.
9.
Remove the cover plate on the left-hand side of the housing.
10. Close the duct on the right-hand side of the housing using the cover plate.
11. Pull the power line through left-hand side of the housing and secure cable duct.
12. Attach the suction lance to the left-hand side of the housing.
13. Connect the suction lance to the metering pump.
14. Connect the suction lance connection cable in the electronics control box.
MAN049250 Rev. 1-01.2021
NOTICE!
Make sure that the power cable does not come into contact with any
sharp parts in the device or with the product.
30

Advertisement

Table of Contents
loading

Table of Contents