Figure 8 - Jack-Up Procedure - York YHAU-CW Manual

Double effect steam-fired absorption chiller
Table of Contents

Advertisement

FORM 155.31-ICOM2.EN.UL
SECTION 3 – HANDLING, STORAGE, INSTALLATION AND REASSEMBLY
ISSUE DATE: 12/21/2018
Operate the front and rear jacks alternately.
Do not jack up the machine more than 0.78 inch at a
time. Each time the machine is jacked up, adhere it
with a suitable crosstie.
Use the jack-up support on the main shell of the body
as shown below. If using a high temperature generator,
use secondary jack-up support.
Jack-up
Crosstie
Jack-up
LD22949_UL

FIGURE 8 - JACK-UP PROCEDURE