Startup

Startup
1. Fill the spool valve ports with compatible lubricant.
Consult with your material supplier to select an
acceptable lubricant. Regularly verify that lubricant
is present.
Spool Valve Ports/Oil Cups
F
. 8: Top View of Valve with Top Section Removed
IG
1. Perform the ratio check procedure. See Ratio
Check on page 17.
2. Install the static mixer and shroud to the metering
valve outlet nose (L) as shown in Figure 9.
F
. 9: Install Static Mixer
IG
16
Metering Rod Ports
3. Pressurize the A and B fluid supply pumps (AA, AB)
connected to the metering valve (AC) to prime the
system. See Model Information on page 3 for max-
imum inlet working pressures.
4. Dispense several full stroke shots until the material
is air-free and has good shut-off at the nose.
NOTE: Very viscous, compressible materials may con-
tinue to drool after the system is primed. Reduce the
flow rate as required to produce air-free dispense.
NOTE: Very thin materials may require tilting the valve
greater than 45 degrees and dispensing shots until the
material is air-free. Remove oil from the spool valve oil
cups before proceeding. See Figure 8.